Environmental permit application for the Suomussalmi talc project submitted to the Regional State Administrative Agency of Northern Finland

The environmental and water permit application for the Suomussalmi talc project was submitted to the Regional State Administrative Agency of Northern Finland on 9 May 2025.

The environmental impacts of the project have previously been assessed in the environmental impact assessment procedure (EIA), as a result of which the coordinating authority, the Kainuu ELY Centre, issued an official statement in November 2024. In the official statement, the coordinating authority took a position on the conclusions and the adequacy of the assessment. The conclusions of the coordinating authority were taken into account in the environmental permit application submitted to the Regional State Administrative Agency of Northern Finland.

Based on the studies of the EIA phase, it was decided to apply for a permit to discharge effluents towards Kivijärvi. Several changes were made to the project plan, for example, to minimize the impact on water bodies. These included changes related to the location of the waste and tailings areas and their base and cover structures. The changes also allowed the size of the mining area expansion to be reduced.

The company’s goal is to enable a modern, carbon-neutral and traceable talc production facility at the current Suomussalmi soapstone quarry and factory site.

News

The results of the resident and stakeholder survey for the talc project highlighted the importance of local cooperation already in the early stages of the project

Nordic Talc Oy organized a resident and stakeholder survey regarding the Suomussalmi talc utilization project. The resident and stakeholder survey is intended to be continued periodically in order to map the views of local people and other stakeholders, especially on the impacts caused by the project on people, and to hear, among other things, expectations and wishes for the implementation of project communication.

Read more »

Nordic Talc and Kajave agreed on planning of a new power line connection

Nordic Talc Oy and Kajave Oy have agreed to start planning a new power line connection. The new power line connection enables the power needed for Nordic Talc’s production. At the same time, it strengthens Ylä-Kainuu’s distribution network and also enables the development of other business activities, tourism and green transition projects in the area.

Read more »

By-product Assessment of the Suomussalmi talc project has been completed

In the project, both the suitability of the by-product of the talc project for further processing, as well as its product properties and utilization possibilities were investigated. The main goals of the project were achieved and, based on the results obtained, it is possible to choose possible methods and application areas suitable for further processing.